Improvement Items for Pleasantview FFY 2007-2008:
1. A/C- Heater combination unit to replace existing wall air conditioner and living room baseboard heater. Completed
2. Tree pruning. Completed
3. Handrails for sloping sidewalks on Avenue D side.
4. Shower replacement in handicap units.
5. New updated fire alarm system.
6. Re-landscape courtyards and all flower areas. Completed
7. 5 new ADA washers and dryers.
8. Cooling system for laundry rooms. Completed
9. New valances for Community room. Completed
10. New banquet tables for Community room. Completed
11. Restripe parking lots.
12. Replace all exterior decking and repair all decking support beams. Completed
13. New Flower boxes for deck railings on 2nd and 3rd floors. Completed
14. Replace apartment fire extinguishers.
15. Storage sheds for garden areas. Completed